Dashboard · Thu, Nov 26

Search
Ac
Ana Cruz
Superuser
Project progress
42%
2 pts ahead of plan · 40%
Latest estimate
₱6,450,000
₱30,000 under budget
Crew on site
8 / 13
First in 6:48 AM
Low stock
3 items
Reorder needed today

This week

Nov 24–30
Balcony slab pour
On track
Friday, Nov 27 · formwork ready for inspection
2F window frames, east wing
In progress
12 of 20 frames on site · install this week
Plumbing rough-in, 1F wet areas
Not started
Starts Mon, Dec 1 · after slab pour

November

Monthly view
2F structural78%
Openings & windows45%
MEP rough-in20%
Overall project42% of 40% plan

Budget vs actual vs LE

All figures in ₱
Category Budget Actual LE LE vs budget
Materials ₱2,850,000 ₱1,920,400 ₱2,980,000 +₱130,000
Labor ₱1,620,000 ₱1,105,800 ₱1,590,000 −₱30,000
Equipment ₱480,000 ₱312,500 ₱465,000 −₱15,000
Subcontractors ₱980,000 ₱420,000 ₱995,000 +₱15,000
Permits & misc. ₱250,000 ₱186,200 ₱240,000 −₱10,000
Contingency ₱300,000 ₱0 ₱180,000 −₱120,000
Total ₱6,480,000 ₱3,944,900 ₱6,450,000 −₱30,000

Crew today

8 present · 5 out
Jd
Jun dela Cruz
6:48
In
As
Arnel Santos
6:51
In
Pm
Paolo Mendoza
6:57
In
Ln
Luis Navarro
7:01
In

Low stock

View all
10mm deformed bars
Min 80 pcs
42
Portland cement Type 1
Min 50 bags
28
Tie wire #16
Min 15 kg
8