Project progress
42%
2 pts ahead of plan · 40%
Latest estimate
₱6,450,000
₱30,000 under budget
Crew on site
8 / 13
First in 6:48 AM
Low stock
3 items
Reorder needed today
This week
Nov 24–30
Balcony slab pour
On track
Friday, Nov 27 · formwork ready for inspection
2F window frames, east wing
In progress
12 of 20 frames on site · install this week
Plumbing rough-in, 1F wet areas
Not started
Starts Mon, Dec 1 · after slab pour
November
Monthly view
2F structural78%
Openings & windows45%
MEP rough-in20%
Overall project42% of 40% plan
Budget vs actual vs LE
All figures in ₱
| Category | Budget | Actual | LE | LE vs budget |
|---|---|---|---|---|
| Materials | ₱2,850,000 | ₱1,920,400 | ₱2,980,000 | +₱130,000 |
| Labor | ₱1,620,000 | ₱1,105,800 | ₱1,590,000 | −₱30,000 |
| Equipment | ₱480,000 | ₱312,500 | ₱465,000 | −₱15,000 |
| Subcontractors | ₱980,000 | ₱420,000 | ₱995,000 | +₱15,000 |
| Permits & misc. | ₱250,000 | ₱186,200 | ₱240,000 | −₱10,000 |
| Contingency | ₱300,000 | ₱0 | ₱180,000 | −₱120,000 |
| Total | ₱6,480,000 | ₱3,944,900 | ₱6,450,000 | −₱30,000 |
Crew today
8 present · 5 out
Jd
Jun dela Cruz
6:48
In
As
Arnel Santos
6:51
In
Pm
Paolo Mendoza
6:57
In
Ln
Luis Navarro
7:01
In
Low stock
View all10mm deformed bars
42
Portland cement Type 1
28
Tie wire #16
8